Project Overview
Former
Cayburry Building
Pittsfield, MA
Project
Objectives
 |
Purchase and demolish a
downtown building |
 |
Identify
current environmental conditions on and under the property |
 |
Remove
asbestos and hazardous materials impacted by demolition |
PROJECT FEATURES
 |
Demolition
of a two-story, downtown building |
 |
Removal
of asbestos pipe insulation, floor coverings, roofing, and exterior stucco |
 |
Removal
of four (4) above ground storage tanks |
PROFESSIONAL
SERVICES
 |
21E
investigation and report |
 |
Pre-demolition
hazardous materials survey |
 |
Coordination
with owner, engineer, and contractor |
 |
Preparation
of contract documents including specifications and cost estimates |
 |
Monitoring
and review of asbestos and hazardous materials removal |
PROJECT SIZE
 |
$150,000
hazardous materials removal and demolition |
PROJECT DURATION
 |
Five
months |
(Click to have receive a no obligation proposal on this
type of work)

|
For More Information Contact:
Eco-Genesis Environmental Consultants
180-1 Elm Street, Suite #201, Pittsfield, MA 01201
Tel: (413) 445-7756
FAX: (413) 499-7438
Internet: info@Ecogenesis.com
|