Project Overview
Former
England Brothers building
Pittsfield, MA
Project
Objectives
 |
Demolish a historic downtown
building to prepare the site for redevelopment |
 |
Remove
asbestos and hazardous materials impacted by demolition |
PROJECT FEATURES
 |
Demolition
of a seven story downtown building |
 |
Removal
of asbestos, pipe insulation, boiler insulation, floor coverings,
terrazzo, and floor leveler |
 |
Removal
of PCB's, freon, water treatment chemicals, and above ground storage
tanks |
PROFESSIONAL
SERVICES
 |
Pre-demolition
hazardous materials survey |
 |
Preparation
of contract documents including specifications and cost estimates |
 |
Coordination
with owner, engineer, and contractor |
 |
Management
of hazardous materials removal work |
 |
Environmental
monitoring and testing |
PROJECT SIZE
 |
160,000
square foot building |
 |
$600,000
hazardous materials removal and demolition |
PROJECT DURATION
 |
Four Months |
(Click to have receive a no obligation proposal on this
type of work)

|
For More Information Contact:
Eco-Genesis Environmental Consultants
180-1 Elm Street, Suite #201, Pittsfield, MA 01201
Tel: (413) 445-7756
FAX: (413) 499-7438
Internet: info@Ecogenesis.com
|